EXECUTIVE SUMMARY

The Integrated Instructional Facility
ACTION ITEM:
The Integrated Instructional Facility (Project No. 95- 7465) - Conceptual Approval
ISSUE:
The University of Arizona requests Conceptual Approval for the Integrated Instructional Facility, UA Project No. 95-7465.
BACKGROUND:
The Arizona Board of Regents granted Project Initiation approval for this building on September 8, 1994.

The University of Arizona proposes to construct an Integrated Instructional Facility (IIF) comprising 50,670 net assignable square feet (NASF) in 84,500 gross square feet (GSF) of new construction. It would serve approximately 4,500 first-year students. The proposed $20.25 million building is considered important for the successful implementation of the University's new first-year initiative. The new undergraduate program is being designed to ensure that University graduates are better prepared to meet the challenges of the 21st century.

Estimated total project cost of 16.9 million submitted at Project Initiation was based on preliminary programming with the construction costs calculated using ABOR Cost Control and Professional Fee Guidelines, Revised October 26, 1992. The revised project cost of $20.25 million reflects detailed project programming based upon programmatic space requirements and site location parameters. Major budget increases are found in Utility Extensions to the central campus project site ($0.6 million), and increased higher construction costs ($2.6 million) using the estimate furnished by an independent cost consultant which more accurately reflects current and projected market conditions.

The IIF concept stems from a planning effort devoted to improving undergraduate education. Goals developed through this effort, as presented to the Board of Regents on September 8, 1994, focus on: increasing first-year student persistence rates, improving graduation rates, increasing first-year student exposure to ranked faculty, alleviating the current classroom space shortfall, and providing state-of-the-art classrooms in a more cost-efficient manner than renovating older facilities. The proposed facility would furnish the necessary space to deliver a common curricular experience, and would furnish an academic/intellectual "home base" for freshman students.

Principal program elements proposed to be incorporated into the new facility include multi-use, state-of-the-art technology lecture halls and classrooms; a Student Support area; and instructional support space. The building integrates multi-media and teaching/learning support systems into a facility that provides flexible space configurations. The facility would also contain: offices for the three program coordinators; Instructional Commons where first-year students, faculty, and graduate teaching assistants can meet; and an Instructional Support Area.

A student support area would include the Instructional Commons, a primary component associated with student support activities. The commons area would be staffed with graduate teaching assistants from each core area. Students would have access to small group study rooms for informal discussions and study sessions, as well as access to the University's computer network. The facility would provide first-year students with access to the services and resources of the University Learning Center, a unit that plays a key role in helping students develop study skills that equip them for success at the University. Academic advising for freshman students would also be situated in close proximity to the Instructional Commons area.

An Instructional Support area would serve as a center for the continuous professional development of the faculty. The area would house technicians to support instructional classroom equipment, and to assist faculty in developing and completing multi-media instructional presentations. It would furnish the necessary environment for faculty members to learn how to utilize state-of-the-art instructional resources and to preview class presentations.

The University of Arizona continues to be deficient in classroom space in both quantitative and qualitative terms. Completion of the IIF would diminish this University-wide space deficit, and provide the necessary surge space for the renovation of existing classroom spaces.

It is proposed to locate the project in the central area of the campus, adjacent to the Main Library (refer to the map on page 12). This location promotes the notion of centrality, and is within reasonable walking distance to existing residence halls, the Student Union, libraries, and other related student support facilities. Two sites are being evaluated to determine the "best fit" from a campus form and function perspective, as well as to optimize programmatic functions of the facility.

Operation and maintenance costs for the facility would be funded from future state appropriations.
SOURCE OF FUNDS:
State appropriations ($16,900,000), Other ($3,350,000).
RECOMMENDATION/CONCLUSION
RESOLVED: The University of Arizona's request for Conceptual Approval for the Integrated Instructional Facility , UA project No. 95-7465, be, and hereby is, approved.
--------------------------------------------------------------------------------

Arizona Board of Regents

PROJECT JUSTIFICATION:
University of Arizona

PROJECT NAME:
Integrated Instructional Facility

DATE:
December 1-2, 1994 Project Number 95-7465

Basic Justification

Project purpose and justification:
This project symbolizes a fundamentally different way of thinking about learning methods and environments. It is structured around five fundamental principles that go beyond the specific orientation inherent in any single building or academic program. These principles are designed to implement an outstanding first-year-experience curriculum, as well as to address current institutional challenges in successfully delivering a general education curriculum. They are as follows:

A. Deliver a common educational experience in support of the first-year curriculum. The Integrated Instructional Facility (IIF) project will provide first-year students with a resource-rich learning environment that would contribute to the development of knowledge, skills, and attitudes of thought that are the foundation of a lifetime commitment to learning, personal development, and social responsibility.

B. Provide freshman students with an academic/intellectual "home base" which is especially important on a large and complex campus. Development of such a campus home base has been found to support student retention.

C. Provide an enriched environment for students that integrates learning support resources and services with campus physical facilities.

D. Facilitate the implementation of "teams and technologies" as key, central components of the curriculum delivery process.

E. Ensure maximum flexibility of student learning environments to support numerous academic programs. A facility would need to accommodate a wide variety of student learning experiences while allowing technological flexibility.

Does this project address fire and life safety issues? Yes
Explain:
The new facility will meet all current University fire and life safety codes, and will meet all ADA criteria.

Is this project designed to correct current deficiencies? Yes
Explain:
The IIF project would address current deficiencies in quality, quantity, and "mix" of classroom space on campus. It is planned to begin remedying, in a significant way, the existing quality of classroom space through the provision of a modern campus "neighborhood center" type of environment, specifically designed to promote stimulating learning interactions. It would enhance the University's quantity and mix of instructional (classroom) space, by creating opportunities for the integration of a wider variety of learning resources both in the classroom and after scheduled class hours. The University's current situation frequently precludes extended faculty/student interactions, group/team study, peer tutoring, access to technological resources, etc. The facility would provide a place for students to meet with faculty and/or other students, to complete assignments, and access information via the campus computer network.

The project would also take advantage of technology access to sophisticated network resources available locally as well as globally. This kind of technological connectivity is out-of-reach for a majority of first-year students in the existing campus environment.

The IIF project would allow the full integration of learning resources in the fundamental classroom experience of first-year students. The proposed facility will also be an attractive building within which the University's ranked faculty would teach, thereby furthering the President's commitment for greater faculty involvement in the student's first-year experience.

Through thoughtful, well-planned siting, the IIF Project will help create a unique learning environment that focuses on the undergraduate experience. Although fully integrated in its internal building and educational support systems, the project will also be integral with the broader campus living/learning environment. Its centrality within the core campus will promote positive adjacencies with other student support facilities such as the Main Library, Student Union, Student Health and Wellness Center, residence halls, and the Student Recreation Center.

The Task Force on Undergraduate Education focused the attention of the campus community upon the first-year experience, observing that "the freshman-year experience is pivotal in fully engaging undergraduate students in the fabric of intellectual, social, and cultural life on campus. The freshman year should be designed to provide a stimulating introduction to academic disciplines, classes (including small group sessions) with professorial faculty, accurate academic advising, and carefully constructed opportunities for out-of-classroom contact with faculty and professional staff".

The existing, deficient configuration of widely dispersed classroom space in aging facilities does not meet these objectives.

Does this project support a strategic objective? Yes
Explain:
There are a number of University strategic objectives that will be furthered by implementing the IIF project. For example, the IIF project will:

Support implementation of the new teaching initiative which addresses University learning strategies such as assessing students' academic preparation, study skills, and motivation; and providing course placement and graduate entrance exams required by academic departments;

Create needed space and a "student-friendly" learning environment;

Address our desire to become a more student-centered university;

Provide technological resources to maximize training for faculty and students which supports achieving a shared University vision; and,

Contribute toward achieving the "Proposed Measurable Goals for Linking Faculty Teaching Efforts to the Improvement of the Quality of Undergraduate Education" presented to the Board at their September, 1994, meeting. The IIF project will promote University success in the retention of our students and graduates in the 21st century. The project will provide a place for students to acquire learning skills beyond just the acquisition of knowledge; a place where students' difficult, often turbulent, transition from high school to university is a challenging and supportive team experience rather than an intimidating solitary one.

The IIF project also has the added benefit of gaining, for the University, valuable experience in the planning, development, and deployment of model learning/technology environments for future application in the renovation of other campus facilities.

What alternatives were considered and why were they rejected?

Alternatives considered include the implementation of a first-year learning curriculum in facilities scattered across campus. This option would fail to provide students with the same centralized shared experience that the University seeks to provide in order to enhance their prospects for academic success. Construction of the proposed facility would furnish surge space essential for the University to complete classroom renovations to accommodate state-of-the-art instructional and informational technology. Therefore, no reasonable alternative to the Integrated Instructional Facility will achieve the University's long-term goals and objectives to improve undergraduate education.

Space and Utilization Information

Space and Population by Program (a)
1 2 3 4

Current Space-(NASF) (b) 294,740 N/A N/A

Students (population or FTE) --- --- ---

Faculty & Staff " " " --- --- ---

Administration " " " --- --- ---

Projected (c) Space, with project (NASF) 336,121(d)16,000 3,870

Students (population or FTE) --- 4,500 ---

Faculty & Staff " " " --- 32 7

Administration " " " --- 0 0

a) Programs correspond to those listed on page 7.
b) Net Assignable Square Feet (NASF).
c) Based upon planned occupancy date.
d) Program 1 includes AME (7,781 NASF) classroom under construction.

Provide relevant space utilization information or other service level data, including current and forecasted, with and without the project.

Comments:

Program 1- Central scheduled classroom space
The facility would add 30,800 NASF of state-of-the-art lecture halls and classroom space to the campus. Completion of the project, along with other facilities currently under construction, would slightly exceed estimated classroom space requirements. Excess space would provide the University with the necessary flexibility to renovate outmoded classrooms, and to reassign areas to address other pressing space requirements based on a detailed University assessment of needs (e.g. class laboratory space is substantially below minimum standards). Student, faculty, staff, and administrative numbers will remain constant with the completion of the Integrated Instructional Facility.

Program 2 - Student Support Space
Three core coordinators will manage faculty teaching within the proposed core curriculum. These coordinators, along with a limited support staff, will be housed in the Integrated Instructional Facility (IIF).

Student support activities are currently provided for all University students by the University Learning Center, Office of Academic Services within the College of Arts and Sciences, and the Center for Computing & Information Technologies (CCIT). A portion of these programs with a freshman orientation would be incorporated within the IIF's Instructional Commons to provide a central support area for first-year students. It would include: open access computer laboratory/study area, tutoring, student mentors, and academic advising. The Instructional Commons would be staffed with teaching assistants to assist students with assignments and computer software as needed.

Program 3- Instructional Support Space
The facility would provide an area for faculty to develop class presentations, enhance teaching skills, and obtain assistance in utilizing state-of-the-art classroom equipment. The area would provide on-call technical support to faculty lectures and media-based presentations.

Arizona Board of Regents
CONCEPTUAL AND PROJECT APPROVAL SUMMARY
University of Arizona

PROJECT NAME: Integrated Instructional Facility

DATE: December 1-2, 1994 Project Number: 95-7465

PROJECT DESCRIPTION :
A new instructional facility that contains multi-use, state-of-the-art lecture halls, classrooms, and instructional support space.

PROPOSED SITE: Central campus: location and configuration to be determined.

Scope:

Total Gross Square Feet 84,500

Net Square Feet: Total 50,670

Classroom 30,800 Classroom Service 2,800

Computer Laboratory 8,000 Study Room 2,600

Office 6,470

Other Applicable Scope Measure (1): Item N/A Quantity

Programs To Be Housed: (Use additional sheets as necessary)


Program Name Net Assignable Square Feet

1. Centrally Scheduled Classrooms 30,800

2. Student Support 16,000

3. Instructional Support 3,870

4. Vacated Space

Amount Of Space To Be Vacated: To be determined
Projected Use Of Vacated Space

Completion of the project would permit the University to renovate existing classroom space to meet its existing space deficit (2). Quantity, location, and space to be reassigned would be determined as part of the Instructional Renovation Projects.


Project Budget Cost

1. Total Capital Cost $20,250,000

2. New Construction Budget 9,444,000

3. New Construction Budget per Gross Sq. Ft 111.76

4. Total Annual Operating Cost 678,700


Funding Source Dollars Per Year ($millions)

FY 1996 FY 1997 FY 1998 FY 1999

State Appropriation, Other $0.53 $4.21 $12.45 $3.06

Project Schedule Date

Begin Finish

Hire Consultants July 95 Sep 95

Design Oct 95 Nov 96

Bidding Dec 96 Feb 97

Construction Mar 97 Sep 98

Occupancy Nov 98

Staffing Plan
Construction Manager (Full Services) Yes X No
In-house Staff Discipline(3) FTEs Months

Comments:
A number of external consultants were retained to assist in planning the proposed facility. Paulien & Associates completed the facilities program report which identifies space requirements; Durrant Roberts/Dinsmore assisted with the Site Suitability Study to identify the optimal building location; and, Andrew Chartwell & Co. produced the construction budgets.

Notes:

(1) Other applicable scope measures may include items such as number of parking spaces for a parking garage or additional cooling capacity for a utility project.

(2) The University's Space Management Information Requirements were presented to the Board at their May 26, 1994, meeting. Total estimated space deficit was 1.35 million NASF. After the completion of the Aerospace and Mechanical Engineering Building currently under construction, the University's space deficit will decrease to approximately 1.25 million NASF.

(3) To be filled in only if full construction manager services are not to be used.

 

--------------------------------------------------------------------------------

UNIVERSITY: University of Arizona

PROJECT NAME:  Integrated Instructional Facility

DATE:  December 1-2, 1994 Project Number 95-7465

DESCRIPTION: New undergraduate classroom building.

ARCHITECT: To be determined.

CONSTRUCTION MANAGER: To be determined.

CONTRACTORS: To be determined.

CURRENT ACTIONS: Conceptual Approval.

SCHEDULE: PROPOSED REVISED ACTUAL

Preliminary Plan Approval Oct 95

Bid Date Dec 96

Const. Period (Calendar Days) 548

Occupancy Date Nov 98

SOURCE OF FUNDS: State Appropriation ($16,900,000), Other ($3,350,000).

PROJECT PRE

CONCEPTUAL APPROVAL CONSTRUCT. FINAL

ESTIMATE ESTIMATE ESTIMATE COST

Capital Costs

1. Land Acquisition $ 0

2. Construction Cost

A. New Construction $ 9,444,000 (1)

B. Remodel/Renovate

C. Special Fixed Equip. 1,398,000 (2)

D. Site Develop. (exc. P&L) 25,000

E. Parking/Landscape. (P&L) 195,000

F. Utilities Extensions 955,000

G. Other 80,000

H. Inflat. Adjust.(39) mos. 2,251,000(3)

Subtotal Construction Cost $14,348,000

3. Fees (% of Constr. Cost)

A. Constr. Manager (4%) $ 574,000

B. Arch./Engineer (8.5%) 1,220,000

C. Other: Reimbursable 430,000

Subtotal Fees $ 2,224,000

4. F/F/E Movable $ 1,510,000 (4)

5. Conting./Design Phase (6%) 892,000

6. Conting./Const. Phase (5%) 717,000

7. Parking Reserve 0

8. Telecomm. Equipment 49,000

Subtotal Items 4-9 $ 3,168,000

9. Additional University Costs

A. Surveys and Tests $ 80,000

B. Move-in Costs 36,000

C. Public Art 72,000

D. Printing Advertisement 36,000

E. Other 286,000(5)

Subtotal Add. Univ. Costs $ 510,000

TOTAL CAPITAL COST $20,250,000

PROJECT PRE

CONCEPTUAL APPROVAL CONSTRUCT. FINAL

ESTIMATE ESTIMATE ESTIMATE COST

Annual Operating Cost

10. Personal Services $ 174,600

11. Operating Costs 58,400

12. Capital Equipment 17,500

13. Utilities 428,200

TOTAL ANNUAL OPERATING COSTS $ 678,700 $ $ $

Probable Costs (Not in Budget)

14. Cost of Req.'d Remodeling $ -- of Vacated Space

15. Major Equip. Not In Budget --

16. Intrm.Housing,Bldg.Occup. --

17. Other Probable Costs: --

TOTAL PROB COSTS (Not in Budget) $ 0 $ $ $

NOTES:

1) Construction cost estimated provided by Andrew Chartwell & Co.,

November 1, 1994.

2) Special Fixed Equipment includes built-in classroom projection equipment and building computer network.

3) Inflation adjustment figure was calculated using the estimate furnished by the independent cost estimator, Andrew Chartwell & Co.

The figure is higher than ABOR's October, 1992, Construction Cost and Professional Fee Guidelines, and is a better reflection of current construction market activities. It assumes that existing conditions would continue over the next few years.

4) F/F/E Movable budget allowance provides the necessary classroom and office furniture, fixtures, and equipment to make the facility fully operational.

5) Other Additional University Costs, line 9E, include:

Facilities Design & Construction costs: $184,000

Facilities Planning costs: $ 30,000

Facilities Management costs: $ 72,000

Total $286,000 COST PER

CATEGORY IDENTIFICATION GSF % GSF EXTENSION

"A" Series A-6 84,500 100.0 $ 38.92 $3,288,740

(Shell)

SUB TOTAL 84,500 100% $ 38.92 $3,288,740

"B" Series B-114 Lecture Hall 31,852 38.0 $ 48.98 $1,560,120

(Interior)

B-112 Classroom 19,512 23.0 33.93 662,027

B-221 Instruct. Commons 13,341 16.0 71.02 947,494

B-110 Group Meeting 4,336 5.0 33.69 146,076

B-310 Office 10,123 12.0 35.21 356,419

B-350 Conference 667 1.0 45.77 30,531

B-221 Faculty Resources 1,418 2.0 71.02 100,671

B-110 Workshop 1,251 1.0 33.69 42,137

B-530 Control Room 2,001 2.0 50.81 101,680

SUB TOTAL 84,500 100% $ 46.71 $3,947,155

TOTAL CONSTR. COST CONTROL (10/92) 84,500 100% $ 80.52 $7,235,895

Inflation adjustment factor from 10/92 to 12/94 = 8.36% $ 604,924

TOTAL ADJUSTED CONSTR. COST 84,500 100% $ 92.79 $7,840,819

New Construction Cost (Line 2.A, page 1) $ 9,444,000

Total GSF 84,500

Imputed Cost per Square Foot $ 111.76


If the Imputed Cost Per Square Foot exceeds the Construction Cost Control total figure, explain the rationale for this discrepancy:

The new construction cost presented on page 9, line 2.A., was developed by an independent cost estimator, Andrew Chartwell & Co., utilizing information presented in the facilities program report and the site analysis study. The difference between total adjusted construction costs (ABOR cost control guidelines), and the new construction cost (independent cost estimate) is $1.6 million or $19.00/GSF. The higher construction costs can be attributed to current construction market conditions.

 


 

 

 

 

 

 

 